50 41st Avenue
Isle of Palms South Carolina
Developer/owner: City of Isle of Palms
Architect(s): N/A
General contractor: Salmons Dredging Corporation (Apparent Low Bidder)
Engineer(s): Applied Technology & Management (ATM)
EPIC Engineering (Marina Utilities)
Estimated completion date: March 2021
Estimated total cost of project: $2.737M (Base Bid)
Project description: The docks along Morgan Creek at the Isle of Palms Marina will be demolished and replaced with new floating docks. New marina utilities including shore power, potable water, marine pumpout, fuel distribution, and fire suppression will be included. The docks have been designed to accommodate a wide variety of users, including resident vessels, charter boats, tour boats, and transient vessels up to 120-ft. in length. The boat ramp staging docks will also be substantially improved and expanded.
Charleston Under Construction publishes periodically online and bi-monthly in the print edition of the Charleston Regional Business Journal.
Click to submit items for Charleston Under Construction.
Click for advertising information about Charleston Under Construction.